Step 1: Go to SE38 then put program name RDDIT076 and run it, then paste your Request/Task and then execute.

Step 2: In a output section there have a Parent Request and it's sub task and there have Stat column which states D and R
D = Modifiable
R = Released


Step 3: To bring back to development section or unreleased you have to make the both task's stat value from R to D.

Step 4: Double click on it and click on edit button and choose D and save it.


 

 

 

 

 

 

 

 

 

 